Stakeholder | Communication |
---|---|
Client: SHL | Weekly email and meeting |
Other team members | Weekly meeting and online chat |
Number | Description | Importance |
---|---|---|
1 | Upgrade the ALDT, simplifying wiring and increasing maintainability | High |
The expected cost was in the region of $1000, including labour.
The parts lists will be sent to Praveen for approval by the finance team. RS components are preferred, though DigiKey were acceptable if required.
Internal reviews, and extensive testing, will ensure that the product is of a high quality.
Design will be done in digital form where possible. Waste will be minimised, and disposed of appropriately.
Event | Outcome | Risk | Controls | Risk |
---|---|---|---|---|
System is faulty | Product presented to client in unusable condition | High | Reduce: Ongoing testing and internal collaboration. Project is only complete when it works | Low |
I don't have the required skills | The product can't be completed, or is completed to a low standard | Medium | Reduce: Continuous learning to fill in knowledge gaps. Consultation with team members | Low |
I don't have enough time | The project is never completed | Medium | Avoid: I can access the lab 24/7. I can work 4 days a week in order to meet team members as required | Low |
I am in a team of 3. Each of us can be easily accessed via Facebook. Together, we have sufficient skill to complete our parts, and therefore the project.
This project should be completed before I leave on holiday.